EirGrid and SONI have published a second revised weekly constraints update for the current Week 43.

The revision reflects two updates. 

Firstly, the revised limit for the Dublin Generation Transmission Constraint [S_NBMIN_DUB_L1] is 1 from 18th October. This is due to generator outages. 

Secondly, Coolkeeragh unit (C30) is ‘must run’ from 19th October for System Security. 

The weekly constraints update is published every Friday evening on the TSO Responsibilities page of SEM-O.com, alongside the current monthly update.