Update to the Committed Outage Programme 2019 published on the SEM-O website under  publications/tso-responsibilities and Generation Outages:

Aghada Peaking Unit 1 (GU_400181) AT1 will take a scheduled outage from 8th July 2019 00:00 - 12th July 23:00.

Aghada Peaking Unit 2 (GU_400182) AT2 will take a scheduled outage from 1st July 00:00 - 5th July 2019 23:00

Aghada Peaking Unit 4 (GU_400183) AT4 will take a scheduled outage from 15th July 2019 00:00 - 19th July 2019 23:00

Aghada Peaking plant have no other scheduled outages in 2019.

Huntstown (GU_400480) HNC will take a scheduled outage from 3rd August 06:00 - 28th August 2019 17:00. 

Moneypoint Unit 1 (GU_400270) MP1 will take a scheduled outage from 9th August 2019 00:00 - 18th August 2019 22:00. The previous scheduled outage from 10th May - 19th May 2019 is now cancelled. 

Moneypoint Unit 2 (GU_400271) MP2 will take a scheduled outage from 26th July 22:00 - 23rd August 2019 22:00. The previous scheduled outage from 26th April - 23rd June is now cancelled. 

Turlough Hill Unit 1, 2, 3, 4 (GU_400360, GU_400361, GU_400362, GU_4003603 respectively) TH1, TH2, TH3, TH4 will take a scheduled outage from 16th May 07:00 - 13th June 2019 17:00. The previous scheduled outages from 3rd - 9th March and 15th - 29th June are now cancelled. Please note an outage of TH1 and TH2 remains scheduled from 26th - 28th November 2019.


Please report any missing/incorrect information to us as soon as possible at OutagePlanning@eirgrid.com.

 

Disclaimer:  REMIT information is being provided to help market participants comply with the EU Regulation on Wholesale Energy Markets Integrity and Transparency (REMIT)  (# 1227/2011)  which specifies that market participants are obliged to fulfill the obligations described in Article 4 (1) and specifically that “Market participants shall publicly disclose in an effective and timely manner inside information which they possess...”.

Whilst it strives to ensure as high a level of accuracy as possible, EirGrid Group makes no warranties or representations of any kind with respect to: (a) the content of this email (including without limitation its quality, accuracy, and completeness), or (b) the content of any other website referred to or accessed by means of a hypertext link through this email.