Revised Weekly Constraints Update
Affected Period
Status
Closed
Category
Balancing
Run type
N/A
Created
30/11/2021 15:43
Last Updated
30/11/2021 15:46
EirGrid and SONI have published
a revised
weekly constraints update for the current Week 48.
The revision notes:
(Removal of load flow control in Dublin area section) The following units are must run during periods of high
demand for the following EWIC export scenarios;
> 0 & ? 150 MW; HNC or HN2
> 150 & ? 350 MW; HN2
> 350 MW; HNC & HN2
The weekly constraints update is published every Friday evening on the General Publications page of SEM-O.com.