Revised Weekly Constraints Update

Affected Period

Status
Closed

Category
Balancing

Run type
N/A

Created
10/05/2022 16:05

Last Updated
10/05/2022 16:07

EirGrid and SONI have published a revised weekly constraints update for the current Week 19 2022.

The revision notes:

  1. (Dublin Generation S_NBMIN_DubNB2): There must be at least 1 large generator on-load at all times in the Dublin area. Required for voltage control. DB1, HNC, HN2
  2. (Dublin Generation S_NBMIN_Dub_NB): There must be at least 2 large generators on-load at all times in the Dublin area. Required for voltage control. This assumes EWIC is operational. DB1, HNC, HN2, PBA, PBB.

The weekly constraints update is published every Friday evening on the General Publications page of SEM-O.com.