Revised Weekly Constraints Update

Affected Period

Status
Closed

Category
Balancing

Run type
N/A

Created
16/05/2022 11:56

Last Updated
16/05/2022 11:59

EirGrid and SONI have published a revised weekly constraints update for the current Week 20 2022.

The revision note:

  1. EWIC import and export NTC to be set to 0 MW due to upcoming forced outage of the interconnector
  2. Both of the following units are must run for load flow control in the Dublin area during scheduled transmission outages on Tuesday the 17th of May, when available: HN2, HNC 

The weekly constraints update is published every Friday evening on the General Publications page of SEM-O.com.