2027/2028 T-4 Capacity Auction Update
Affected Period
Status
Closed
Category
Capacity
Run type
Created
31/08/2023 14:13
Last Updated
21/09/2023 14:42
Dear
Market Participants,
In
accordance with D.2.1.16 of the Capacity Market Code, the Regulatory
Authorities have instructed the System Operators to publish an updated Capacity
Auction Timetable for the 2027/2028 T-4 Capacity Auction. In accordance to
paragraph D.2.1.11 of the Capacity Market Code (CMC), an updated version of the
timetable is available here.
The
amended timetable moves the Capacity Auction Run Start Date out by 4 weeks. The
reason for this change is due to the TSOs managing a high number of key
operational priorities within the Capacity Market workstream. The table below
shows the impact of the delay on the impacted milestones.
Milestone |
Previous Timetable Date |
Amended Timetable Date |
Final
Qualification Submission Date |
16/08/23 |
14/09/23 |
Final
Locational Capacity Constraint Limits Date |
07/09/23 |
05/10/23 |
Final
Qualification Results Date |
07/09/23 |
05/10/23 |
Qualification
Results Publication Date |
07/09/23 |
05/10/23 |
Final
Auction Information Pack Date |
07/09/23 |
05/10/23 |
Capacity
Auction Submission Commencement |
21/09/23 |
19/10/23 |
Capacity
Auction Submission End |
28/09/23 |
26/10/23 |
Capacity
Auction Run Start |
28/09/23 |
26/10/23 |
Capacity
Auction Completion Date |
03/10/23 |
01/11/23 |
Capacity
Auction Provisional Results Date |
03/10/23 |
01/11/23 |
Capacity
Auction Provisional Results Publication Date |
10/10/23 |
08/11/23 |
Capacity
Auction Approval Date |
02/11/23 |
05/12/23 |
Capacity
Auction Results Date |
09/11/23 |
05/12/23 |
Performance
Security Date |
21/12/23 |
16/01/24 |
We
apologise for any inconvenience this may have caused.
If you have any questions on the above, please contact do
not hesitate to contact us.
Regards,
Capacity Market Team