2028/2029 T-4 Capacity Auction - Provisional SO Qualification Decisions

Affected Period

Status
Closed

Category
Capacity

Run type

Created
16/08/2024 19:56

Last Updated
22/08/2024 15:39

Dear Capacity Market Participants,

Please be advised that the Provisional SO Qualification Decisions for the 2028/2029 T-4 Capacity Auction are now available to be viewed on the Capacity Market Platform (CMP). Where the System Operators have included a Code (i.e. any ALL_CAPS text) in the Qualification Notes in the Participant Qualification Report screen in CMP, please refer to the Provisional Qualification Results Codes for a guide to exporting these qualification notes and an explanation on the meanings of the codes used. If you have been approved by the Regulatory Authorities for a 10 year Maximum Capacity Duration, this will be reflected in the Final Qualification Decisions.

Please be advised that for those units seeking to secure a Grid Connection offer under CRU202437 (The "CRU Direction"), information on the status of planning and landowner consents are required to be submitted to the System Operators by 9th October 2024 in advance of the Final Qualification Submission Date.

Please note that the System Operators Qualification Decisions are provisional. Where your application was rejected or you disagree with the Provisional SO Qualification Decision, Participants may request that the System Operators review the rejection or Provisional SO Qualification Decision (Reviewable Decision) by lodging an Application for Review with the System Operators. The System Operators are keen to work with Participants to the maximum extent provided for under the Capacity Market Code.

In this regard, in the event that you seek a Review of a Provisional SO Qualification Decision, please provide any further information or relevant documentation that you believe would support your position. Applications for Review must be submitted to capacitymarketreviews@sem-o.com no later than Tuesday 20th August 2024, with any non-compliant Application for Reviews being reject by the Wednesday 21st August 2024. All other dates remain as per the Capacity Auction Timetable (CAT2829T-4).

Finally, the System Operators apologise for the delay in the issuing of these Provisional Qualification Decisions and any inconvenience that this may have caused. Please contact the team at capacitymarket@sem-o.com if you have any queries in relation to your Qualification Decision.

Kind regards,

Capacity Market Team