Revised Weekly Constraints Update
Affected Period
Status
Closed
Category
Balancing
Run type
Created
16/09/2024 11:54
Last Updated
16/09/2024 11:56
Dear Market Participant,
EirGrid and SONI have published a revised weekly constraints update for
the current Week 38 2024.
The revision note:
The below temporary Transmission Constraint Group note has
been added:
MP1 and MP2 are must run when
wind generation < 1000 MW
Kind regards,
SEMO Team