Revised Weekly Constraints Update

Affected Period

Status
Closed

Category
Balancing

Run type

Created
30/09/2024 10:48

Last Updated
30/09/2024 11:00

Dear Market Participant,

Please be advised that EirGrid and SONI have published a revised weekly constraints update for the current Week 40 2024.

The revision note:

The below temporary Transmission Constraint Group note has been changed:

  • Units DB1, HNC, HN2 & GI4 are to be made 'must run' while unit PBA has been removed from the 'must run' requirement.

The weekly constraints update is published every Friday evening on the General Publications page of SEM-O.com. 

Kind regards, 