Revised Weekly Constraints Update

Affected Period

Status
Closed

Category
Balancing

Run type
N/A

Created
07/02/2024 17:26

Last Updated
07/02/2024 17:27

Dear Market Participant, 

EirGrid and SONI have published a revised weekly constraints update for the current Week 06 2024.

The revision note:

The below Constraint Note has been removed from the report as testing is no longer required :

Each of the following units are must run when available for reliability stress testing on TEG unit DG1 (7th February 2024 between 08:30 - 12:30): HN2, HNC. Following completion of testing this must run requirement will be removed.

Please note the above date of 7th February 2024 was incorrect and was due to take place tomorrow, 8th February 2024.

The weekly constraints update is published every Friday evening on the General Publications page of SEM-O.com.

Kind regards, 