Revised Weekly Constraints Update
Affected Period
Status
Closed
Category
Balancing
Run type
Created
07/03/2024 11:56
Last Updated
07/03/2024 12:20
Dear Market Participant,
EirGrid and SONI have published
a revised
weekly constraints update for the current Week 10 2024.
The revision note:
The below Constraint Note has been updated to include MP5:
There must be at least one unit on load at all times; required to support the 400kV network. Note this TCG is currently set to 0 for all system conditions as the requirements are
The weekly constraints update is published every Friday
evening on the General
Publications page of SEM-O.com.
Kind regards,