Revised Weekly Constraints Update

Affected Period

Status
Closed

Category
Balancing

Run type

Created
07/03/2024 11:56

Last Updated
07/03/2024 12:20

Dear Market Participant,

EirGrid and SONI have published a revised weekly constraints update for the current Week 10 2024.

The revision note:

The below Constraint Note has been updated to include MP5:

There must be at least one unit on load at all times; required to support the 400kV network. Note this TCG is currently set to 0 for all system conditions as the requirements are 

The weekly constraints update is published every Friday evening on the General Publications page of SEM-O.com. 

Kind regards,

SEMO Team