Ad-Hoc For an Upheld Formal Query - CRM
Affected Period
May 2025, June 2025, Aug 2025, Sep 2025, Oct 2025, Nov 2025, Dec 2025, Jan 2026, Feb 2026, Mar 2026
Status
Closed
Category
Settlement
Run Type
Ad hoc (Settlement)
Created
Last Updated
Dear Participants,
Please be advised that due to an upheld formal query with high materiality, SEMO will be running and publishing an Ad-Hoc settlement of CRM only for the below billing periods.
The below months will be included in the Settlement Document due for publication on 10/08/2026
- May 2025
- June 2025
- August 2025
- September 2025
- October 2025
The below months will be included in the Settlement Document due for publication on 14/08/2026
- November 2025
- December 2025
- January 2026
- February 2026
- March 2026
These updates were included in the Settlement Calendar published on 29/07/2026.
Kind Regards