Updated message 09/05/2025 20:25;

 

Dear Market Participants,

The need for EirGrid TSO to dispatch TEG in north Dublin no longer applies, effective 20:05 on 09/05/25.

Kind Regards,

SEMO Trading Operations

 

Original Message 08/05/2025;

 

Dear Market Participants,

 

The TSO has dispatched Temporary Emergency Generation (TEG) in north Dublin in order to manage local transmission constraints, effective 22:13 on 08/05/25.

 

A further communication will be issued when the need to dispatch TEG in north Dublin no longer applies.

 

Kind Regards,

SEMO Trading Operations