REMIT Update

Affected Period
19/10/2026 - 30/10/2026

Status
Open

Category
European Transparency

Run Type
N/A

Created

Last Updated

Lisdrum BAT LF1 (GU_404900) will be disconnected and unable to export energy to the transmission system to facilitate essential transmission work from Monday, 19 October 2026 until Friday, 30 October 2026.

 

Disclaimer: REMIT information is being provided to help market participants comply with the EU Regulation on Wholesale Energy Markets Integrity and Transparency (REMIT)  (# 1227/2011)  which specifies that market participants are obliged to fulfill the obligations described in Article 4 (1) and specifically that “Market participants shall publicly disclose in an effective and timely manner inside information which they possess...”. 

Whilst it strives to ensure as high a level of accuracy as possible, EirGrid Group makes no warranties or representations of any kind with respect to: (a) the content of this email (including without limitation its quality, accuracy, and completeness), or (b) the content of any other website referred to or accessed by means of a hypertext link through this email.