Revised Weekly Constraints Update

Affected Period

Status
Closed

Category
Balancing

Run Type

Created

Last Updated

Dear Market Participant,

EirGrid and SONI have published a revised weekly constraints update for the current Week 32 2025

The following Transmission Constraint Groups have been added: 

  • S_NBMIN_MINTRL7
  • S_NBMIN_MINNI4

The following Transmission Constraint Groups have been updated:

  • S_MWR_ROI
  • S_MWR_NI
  • S_NBMIN_MINNIU 

Reason: 

Implementation of Northern Ireland Two-Set Trial. 

The weekly constraints update is published every Friday evening on the General Publications page of SEM-O.com. 

Kind regards,

SEMO Team