SDP-02 (ESPS) Update & SDP Solution Overview Document V2
Affected Period
Status
Closed
Category
Balancing
Run Type
Created
Last Updated
Dear Market Participant,
Please see below update on the SDP-02 (ESPS) initiative.
SDP-02 (ESPS) Delivery Update
The SDP programme is progressing with cutover activity to support the SDP-02 go-live, as planned.
EMS deployment is underway with MMS code deployment scheduled to take place on 10th November, as per the cutover plan.
A further cutover progress update will be provided in advance of the conversion of ESPS units from ‘Multi-Fuel’ to ‘Battery Storage’ on 12th November. (ESPS units will become effective as ‘Battery Storage’ units from 23:00 on 12th November).
Overview of SDP Solution for Battery Units V2 Document
In preparation for the upcoming SDP-02 go-live, the Overview of SDP Solution for Battery Units V2 has now been published on the SEMO website (here). This updated document provides enhanced clarity and guidance on the SDP solution for battery units.
If you have any questions or require further information, please contact schedulinganddispatch@eirgrid.com or schedulinganddispatch@soni.ltd.uk.
Kind regards,
SEMO Team